[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894709":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894709,580,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》GB 50854-2013，措施项目工程量的计算规则，正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","垂直运输可按施工工期日历天数计算",true,{"key":16,"text":17,"correct":18},"B","垂直运输可按建筑物高度计算",false,{"key":20,"text":21,"correct":18},"C","超高施工增加按建筑物超高部分的高度计算",{"key":23,"text":24,"correct":14},"D","大型机械设备进出场及安拆按使用机械设备的数量计算",{"key":26,"text":27,"correct":14},"E","施工排水、降水按排水、降水日历天数计算","ADE","垂直运输可按建筑面积计算也可以按施工工期日历天数计算，以天为单位。单层建筑物檐口高度超过 20m，多层建筑物超过 6层时，可按超高部分的建筑面积计算超高施工增加。排水、降水以昼夜（24h）为单位计量，按排水、降水日历天数计算。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]