[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894673":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894673,580,2,"多选题","施工组织总设计中，施工部署需要对总体施工方案进行拟定，这些项目通常有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工期长的分项工程",true,{"key":16,"text":17,"correct":14},"B","工程量大的分项工程",{"key":19,"text":20,"correct":14},"C","施工难度大的分项工程",{"key":22,"text":23,"correct":24},"D","对全局影响性不大的分项工程",false,{"key":26,"text":27,"correct":24},"E","对整个建设项目的建成不起关键性作用的工程","ABC","本题考查的是施工组织总设计。施工组织总设计中要拟定一些主要工程项目的施工方案。这些项目通常是建设项目中工程量大、施工难度大、工期长，对整个建设项目的建成起关键性作用的建筑物（或构筑物），以及全场范围内工程量大、影响全局的特殊分项工程",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]