[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894672":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894672,580,2,"多选题","施工组织总设计、单位工程施工组织设计和分部（分项）工程施工组织设计的区别有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制原则和目标不同",false,{"key":16,"text":17,"correct":18},"B","编制的对象和范围不同",true,{"key":20,"text":21,"correct":18},"C","编制的依据不同",{"key":23,"text":24,"correct":18},"D","编制主体不同",{"key":26,"text":27,"correct":18},"E","编制深度要求不同","BCDE","本题考查的是土石方工程施工技术。施工组织总设计、单位工程施工组织设计和分部（分项）工程施工组织设计的区别：编制原则一致；编制内容相通；编制范围、依据、深度、责任主体、作用不同。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]