[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894619":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894619,580,2,"多选题","为有利于措施费的确定和调整,根据现行工程量计算规范。适宜釆用单价措施项目计价的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","夜间施工增加费",false,{"key":16,"text":17,"correct":14},"B","二次搬运费",{"key":19,"text":20,"correct":21},"C","施工排水、降水费",true,{"key":23,"text":24,"correct":21},"D","超高施工增加费",{"key":26,"text":27,"correct":21},"E","垂直运输费","CDE","有些措施项目是可以计算工程量的项目，如脚手架工程，混凝土模板及支架（撑），垂直运输、超高施工增加，大型机械设备进出场及安拆，施工排水、降水等，这类措施项目按照分部分项工程项目清单的方式采用综合单价计价，更有利于措施费的确定和调整。措施项目中可以计算工程量的项目（单价措施项目）宜采用分部分项工程量清单的方式编制。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]