[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894617":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894617,580,2,"多选题","关于当事人对建设工程实际竣工日期有争议时竣工日期确定的说法，正确的有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建设工程经竣工验收合格的，以竣工验收合格之日为竣工日期",true,{"key":16,"text":17,"correct":14},"B","承包人已经提交竣工验收报告，发包人拖延验收的，以承包人提交验收报告之日为竣工日期",{"key":19,"text":20,"correct":14},"C","建设工程未经竣工验收，发包人擅自使用的，以转移占有建设工程之日为竣工日期",{"key":22,"text":23,"correct":24},"D","建设工程整改后竣工验收合格的，以提交竣工验收申请报告的日期为竣工日期",false,{"key":26,"text":27,"correct":24},"E","建设工程未经竣工验收，发包人擅自使用的，以工程完工日期为竣工日期","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]