[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894614":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894614,580,2,"多选题","关于预算定额编制的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预算定额的计量单位一般按工序或施工过程确定",false,{"key":16,"text":17,"correct":18},"B","在综合施工定额的过程中要增加两种定额间的水平差",true,{"key":20,"text":21,"correct":14},"C","人工工日消耗量等于基本用工、辅助用工和人工幅度差之和",{"key":23,"text":24,"correct":18},"D","材料消耗量包括净用量和以净用量为基数计算的损耗量",{"key":26,"text":27,"correct":18},"E","以小组产量计算机械台班产量的，不再计算机械幅度差","BDE","A项，预算定额的计量单位的选择，也要以施工定额为参考。C项，人工工日消耗量包括的基本用工、其他用工两部分组成的。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]