[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894613":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894613,580,2,"多选题","确定预算定额人工工日消耗量过程中，应计入其他用工的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","材料二次搬运用工",true,{"key":16,"text":17,"correct":14},"B","电焊点火用工",{"key":19,"text":20,"correct":21},"C","按劳动定额规定应增（减）计算的用工",false,{"key":23,"text":24,"correct":14},"D","临时水电线路移动造成的停工",{"key":26,"text":27,"correct":21},"E","完成某一分项工程所需消耗的技术工种用工","ABD","预算定额中人工工日消耗量是指在正常施工条件下，生产单位合格产品所必需消耗的人工工日数量，是由分项工程所综合的各个工序劳动定额包括的基本用工、其他用工两部分组成的。基本用工是完成一定计量单位的分项工程或结构构件的各项工作过程的施工任务所必需消耗的技术工种用工，包括完成定额计量单位的主要用工以及按劳动定额规定应增（减）计算的用工量。其他用工是辅助基本用工消耗的工日，包括超运距用工、辅助用工和人工幅度差用工。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]