[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894610":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894610,580,2,"多选题","下列与施工机械工作相关的时间中，应包括在预算定额机械台班消耗量中，但不包括在施工定额中的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","低负荷下工作时间",false,{"key":16,"text":17,"correct":18},"B","机械施工不可避免的工序间歇",true,{"key":20,"text":21,"correct":18},"C","机械维修引起的停歇时间",{"key":23,"text":24,"correct":18},"D","开工时工作量不饱满所损失的时间",{"key":26,"text":27,"correct":14},"E","不可避免的中断时间","BCD","本题考查的是预算定额及其基价编制。选项 A 在定额中不考虑，选项 E 属于施工定额中。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]