[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894606":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894606,580,2,"多选题","施工图预算审查的重点包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","审查相关的技术规范是否有错误",false,{"key":16,"text":17,"correct":18},"B","审查工程量计算是否准确",true,{"key":20,"text":21,"correct":18},"C","审查施工图预算编制中定额套用是否恰当",{"key":23,"text":24,"correct":18},"D","审查各项收费标准是否符合现行规定",{"key":26,"text":27,"correct":14},"E","审查施工图设计方案是否合理","BCD","施工图预算审查的重点是工程量计算是否准确，定额套用、各项取费标准是否符合现行规定或单价计算是否合理等方面。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]