[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894599":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894599,580,2,"多选题","关于工程施工项目最高投标限价编制的注意事项，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","未采用工程造价管理机关发布的工程造价信息时，应予以说明",true,{"key":16,"text":17,"correct":18},"B","施工机械设备的选型应本着经济实用、平均有效的原则确定",false,{"key":20,"text":21,"correct":18},"C","暂估价中的材料单价应通过市场调查确定",{"key":23,"text":24,"correct":14},"D","不可竞争措施项目费应按国家有关规定计算",{"key":26,"text":27,"correct":14},"E","竞争性措施项目费应依据经专家论证确认的施工组织设计或实施方案确定","ADE","B项，施工机械设备的选型应本着经济实用、先进高效的原则确定；C项，暂估价中的材料单价应根据工程造价管理部门发布的价格确定，工程造价信息部门未分布的，可参考市场价格估算。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]