[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894595":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894595,580,2,"多选题","关于投标报价编制的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投标人可委托有相应资质的工程造价咨询人编制投标价",true,{"key":16,"text":17,"correct":18},"B","投标人可依据市场需求对所有费用自主报价",false,{"key":20,"text":21,"correct":14},"C","投标人的投标报价不得低于其工程成本",{"key":23,"text":24,"correct":18},"D","投标人的某一子项目报价高于招标人相应基准价的应予废标",{"key":26,"text":27,"correct":14},"E","应该以施工方案、技术措施等作为投标报价计算的基本条件","ACE","A项，投标价应由投标人或受其委托具有相应资质的工程造价咨询人编制。B项，投标报价由投标人自主确定，但必须执行《建设工程工程量清单计价规范》（GB 50500—2013）的强制性规定。C项，投标人的投标报价不得低于工程成本。D项，投标人的投标报价高于最高投标限价的应予废标。E项，应该以施工方案、技术措施等作为投标报价计算的基本条件。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]