[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894594":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894594,580,2,"多选题","在投标报价时，企业要根据自身的优劣势和招标项目的特点来确定报价策略，通常情况下报价可适当低一些的工程有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","特殊的工程",false,{"key":16,"text":17,"correct":18},"B","竞争对手多，竞争激烈的工程",true,{"key":20,"text":21,"correct":14},"C","专业要求高的技术密集型工程",{"key":23,"text":24,"correct":18},"D","非急需工程",{"key":26,"text":27,"correct":18},"E","投标单位急于打入某一市场、某一地区","BDE","投标单位遇到下列情形时，其报价可适当低一些：①施工条件好的工程；②工作简单、工程量大但其他投标人都可以做的工程；③投标单位急于打入某一市场、某一地区，或虽已在某一地区经营多年，但即将面临没有工程的情况，机械设备等无工地转移时；④本公司在附近有工程，而本项目又可利用该工地的设备、劳务，或有条件短期内突击完成的工程；⑤竞争对手多，竞争激烈的工程；⑥非急需工程；⑦支付条件好的工程。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]