[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894590":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894590,580,2,"多选题","根据《建设工程工程量清单计价规范》（GB50500-2013），关于工程变更价款的调整方法，下列说法中正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程变更导致已标价工程量清单项目的工程量变化小于15%，仍采用原价格",true,{"key":16,"text":17,"correct":18},"B","已标价的工程量清单中没有相同或类似的工程变更项目，由发包人提出变更工程项目的总价和单价",false,{"key":20,"text":21,"correct":14},"C","安全文明施工费按照实际发生变化的措施项目并依据国家或省级、行业建设主管部门的规定进行调整",{"key":23,"text":24,"correct":14},"D","采用单价方式计算的措施费，按照分部分项工程费的调整方法确定变更单价",{"key":26,"text":27,"correct":18},"E","按系数计算的措施项目费均应按照实际发生变化的措施项目调整，系数不得浮动","ACD","已标价工程量清单中有适用于变更工程项目的，且工程变更导致的该清单项目的工程数量变化不足 15%时，采用该项目的单价；安全文明施工费，按照实际发生变化的措施项目调整，不得浮动；采用单价计算的措施项目费，按照实际发生变化的措施项目按前述分部分项工程费的调整方法确定单价。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]