[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894588":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894588,580,2,"多选题","关于施工期间合同暂估价的调整，下列做法中正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不属于依法必须招标的材料，应直接按承包人自主采购的价格调整暂估价",false,{"key":16,"text":17,"correct":18},"B","属于依法必须招标的工程设备，以中标价取代暂估价",true,{"key":20,"text":21,"correct":14},"C","属于依法必须招标的专业工程，承包人不参加投标的，应由承包人作为招标人，组织招标的费用一般由发包人另行支付",{"key":23,"text":24,"correct":18},"D","属于依法必须招标的专业工程，承包人参加投标的，应由发包人作为招标人，同等条件下优先选择承包人中标",{"key":26,"text":27,"correct":18},"E","不属于依法必须招标的专业工程，应按工程变更事件的合同价款调整方法确定专业工程价款","BDE","本题考查的是物价变化类合同价款调整事项。选项A错误，不属于依法必须招标的材料，由承包人采购，发包人确认后取代暂估价，调整合同价款；选项C错误，组织招标的费用被认为包括在承包人签约合同价。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]