[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894583":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894583,580,2,"多选题","编制建设项目竣工决算必须满足的条件包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","经批准的初步设计所决定的工程内容已完成",true,{"key":16,"text":17,"correct":14},"B","单项工程或建设项目竣工结算已完成",{"key":19,"text":20,"correct":21},"C","收尾工程竣工结算已完成",false,{"key":23,"text":24,"correct":14},"D","预留费用不超过规定比例",{"key":26,"text":27,"correct":14},"E","涉及工程质量纠纷事项已处理完毕","ABDE","编制工程竣工决算应具备下列条件： （1）经批准的初步设计所确定的工程内容已完成； （2）单项工程或建设项目竣工结算已完成； （3）收尾工程投资和预留费用不超过规定的比例； （4）涉及法律诉讼、工程质量纠纷的事项已处理完毕； （5）其他影响工程竣工决算编制的重大问题已解决。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]