[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894578":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894578,580,2,"多选题","关于编制工程量清单其他项目费报价的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","暂列金额按招标人在其他项目清单中列出的金额填写",true,{"key":16,"text":17,"correct":18},"B","材料暂估价由投标人根据实际情况自主确定",false,{"key":20,"text":21,"correct":14},"C","总承包服务费由投标人根据招标文件中列出的内容和提出的要求自主确定",{"key":23,"text":24,"correct":18},"D","专业工程暂估价由投标人根据施工组织设计或施工方案自主确定",{"key":26,"text":27,"correct":14},"E","计日工按招标人在其他项目清单中列出的项目和数量，由投标人自主确定综合单价并计算计日工费用","ACE","A项，其他项目费中的暂列金额应按招标人在其他项目清单中列出的金额填写，不得变动。BD两项，材料暂估价应按招标人在其他项目清单中列出的单价计入综合单价，专业工程暂估价应按招标人在其他项目清单中列出的金额填写。C项，总承包服务费应依据招标人在招标文件中列出的分包专业工程内容和供应材料、设备情况，按照招标人提出的协调、配合与服务要求和施工现场管理需要自主确定。E项，计日工应按照其他项目清单列出的项目和估算的数量，自主确定各项综合单价并计算费用。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]