[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894575":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894575,580,2,"多选题","工程量清单是（ ）的依据。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进行工程索赔",true,{"key":16,"text":17,"correct":18},"B","编制项目投资估算",false,{"key":20,"text":21,"correct":14},"C","编制最高投标限价",{"key":23,"text":24,"correct":14},"D","支付工程款",{"key":26,"text":27,"correct":14},"E","办理竣工结算","ACDE","工程量清单是工程量清单计价的基础，贯穿于建设工程的招投标阶段和施工阶段，是编制最高投标限价、投标报价、计算工程量、支付工程款、调整合同价款、办理竣工结算以及工程索赔等的依据。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]