[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894574":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894574,580,2,"多选题","关于分部分项工程量清单的编制，下列说法中正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","以清单计算规范附录中的名称为基础，结合具体工作内容补充细化项目名称",false,{"key":16,"text":17,"correct":14},"B","清单项目的工作内容在招标工程量清单的项目特征中加以描述",{"key":19,"text":20,"correct":21},"C","有两个或以上计量单位时，选择最适宜表现项目特征并方便计量的单位",true,{"key":23,"text":24,"correct":21},"D","除另有说明外，清单项目的工程量应以实体工程量为准，各种施工中的损耗和需要增加的工程量应在单价中考虑",{"key":26,"text":27,"correct":14},"E","在工程量清单中应附补充项目名称、项目特征、计量单位和工程量","CD","项目名称的细化通常结合具体项目特征补充，故 A 错误；在编制分部分项工程量清单时，工作内容通常无需描述，故 B 错误；在工程量清单中应附补充项目的项目名称、项目特征、计量单位、工程量计算规则和工作内容,故 E 错误。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]