[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894573":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894573,580,2,"多选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），关于分部分项工程项目清单的编制，下列说法中正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目编码应按照计算规范附录给定的编码",false,{"key":16,"text":17,"correct":14},"B","项目名称应按照计算规范附录给定的名称",{"key":19,"text":20,"correct":21},"C","项目特征描述应满足确定综合单价的需要",true,{"key":23,"text":24,"correct":14},"D","补充项目应有两个或两个以上的计量单位",{"key":26,"text":27,"correct":21},"E","工程量计算应按一定顺序依次进行","CE","关于 A 选项，分部分项工程量清单的项目编码，应根据拟建工程的工程量清单项目名称设置。关于 B 选项，分部分项工程量清单的项目名称应按专业工程计量规范附录的项目名称结合拟建工程的实际确定。关于 D 选项，当附录中有两个或两个以上计量单位的，应结合拟建工程项目的实际选择其中一个确定。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]