[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894572":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894572,580,2,"多选题","应予计量的措施项目费包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","垂直运输费",true,{"key":16,"text":17,"correct":14},"B","排水、降水费",{"key":19,"text":20,"correct":21},"C","冬雨季施工增加费",false,{"key":23,"text":24,"correct":21},"D","临时设施费",{"key":26,"text":27,"correct":14},"E","超高施工增加费","ABE","应予计量的措施项目包括脚手架费、混凝土模板及支架费、垂直运输费、超高施工增加费、大型机械设备进出场及安拆费、施工排水降水。因此 ABE 正确。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]