[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894559":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894559,580,2,"多选题","《房屋建筑与装饰工程工程量计算规范》GB50854—2013对以下措施项目详细列明了项目编码、项目特征、计量单位和计算规则的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","夜间施工",false,{"key":16,"text":17,"correct":14},"B","已完工程及设备保护",{"key":19,"text":20,"correct":21},"C","超高施工增加",true,{"key":23,"text":24,"correct":21},"D","施工排水、降水",{"key":26,"text":27,"correct":21},"E","混凝土模板及支架","CDE","措施项目中可以计算工程量的项目（如脚手架工程，混凝土模板及支架，垂直运输，超高施工增加，大型机械设备进出场及安拆，施工排水、降水等）宜采用分部分项工程项目清单的方式编制;不能计算工程量的项目（如安全文明施工费，夜间施工，非夜间施工照明，二次搬运，冬雨季施工，地上、地下设施和建筑物的临时保护设施，已完工程及设备保护等）以\"项\"为计量单位进行编制。分部分项工程量清单的组成有项目编码、项目名称、项目特征、计量单位和工程量计算规则。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]