[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894557":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894557,580,2,"多选题","为了便于措施项目费的确定和调整，通常采用分部分项工程量清单方式编制的措施项目有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","脚手架工程",true,{"key":16,"text":17,"correct":14},"B","垂直运输工程",{"key":19,"text":20,"correct":21},"C","二次搬运工程",false,{"key":23,"text":24,"correct":21},"D","已完工程及设备保护",{"key":26,"text":27,"correct":14},"E","施工排水降水","ABE","措施项目中可以计算工程量的项目（如脚手架工程，混凝土模板及支架，垂直运输，超高施工增加，大型机械设备进出场及安拆，施工排水、降水等）宜采用分部分项工程项目清单的方式编制;不能计算工程量的项目（如安全文明施工费，夜间施工，非夜间施工照明，二次搬运，冬雨季施工，地上、地下设施和建筑物的临时保护设施，已完工程及设备保护等）以\"项\"为计量单位进行编制。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]