[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894554":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894554,580,2,"多选题","根据《建设工程工程量清单计价规范》（GB 50500—2008），现浇混凝土工程量计算正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","构造柱工程量包括嵌入墙体部分",true,{"key":16,"text":17,"correct":18},"B","梁工程量不包括伸入墙内的梁头体积",false,{"key":20,"text":21,"correct":14},"C","墙体工程量包括墙垛体积",{"key":23,"text":24,"correct":14},"D","有梁板按梁、板体积之和计算工程量",{"key":26,"text":27,"correct":14},"E","无梁板伸入墙内的板头和柱帽并入板体积内计算","ACDE","根据《房屋建筑与装饰工程工程量计算规范》（GB 50854—2013）附录E的规定，B项，现浇混凝土梁按设计图示尺寸以体积“m3”计算，不扣除构件内钢筋、预埋铁件所占体积，伸入墙内的梁头、梁垫并入梁体积内。A项，构造柱按全高计算，嵌接墙体部分（马牙槎）并入柱身体积。C项，现浇混凝土墙按设计图示尺寸以体积“m3”计算。不扣除构件内钢筋，预埋铁件所占体积，扣除门窗洞口及单个面积大于0.3m2的孔洞所占体积，墙垛及突出墙面部分并入墙体体积内计算。DE两项，有梁板（包括主、次梁与板）按梁、板体积之和计算，无梁板按板和柱帽体积之和计算，各类板伸入墙内的板头并入板体积内计算，薄壳板的肋、基梁并入薄壳体积内计算。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]