[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894550":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894550,580,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》（GB 50854～2013）规定，以下关于措施项目工程量计算，说法正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","垂直运输费用，按施工工期日历天数计算",true,{"key":16,"text":17,"correct":14},"B","大型机械设备进出场及安拆，按使用数量计算",{"key":19,"text":20,"correct":14},"C","施工降水成井，按设计图示尺寸以钻孔深度计算",{"key":22,"text":23,"correct":24},"D","超高施工增加，按建筑物总建筑面积计算",false,{"key":26,"text":27,"correct":14},"E","雨篷混凝土模板及支架，按外挑部分水平投影面积计算","ABCE","选项 D，超高施工增加的工程量计算按建筑物超高部分的建筑面积计算。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]