[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894549":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894549,580,2,"多选题","《房屋建筑与装饰工程工程量清单计算规范》（GB50854-2013）对以下措施项目详细列明了项目编码、项目特征、计量单位、计算规则（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","夜间施工",false,{"key":16,"text":17,"correct":14},"B","已完工程及设备保护",{"key":19,"text":20,"correct":21},"C","超高施工增加",true,{"key":23,"text":24,"correct":21},"D","施工排水、降水",{"key":26,"text":27,"correct":21},"E","砼模板及支架","CDE","规范中给出了脚手架、混凝土模板及支架、垂直运输、超高施工增加、大型机械设备进出场及安拆、施工降水及排水、安全文明施工及其他措施项目的计算规则或应包含范围。除安全文明施工及其他措施项目外，前 6 项都详细列出了项目编码、项目名称、项目特征、工程量计算钡则、工作内容，其清单的编制与分部分项工程一致。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]