[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894536":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894536,580,2,"多选题","根据《建设工程工程量清单计价规范》，以下建筑工程工程量计算，正确的说法是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","砖围墙如有混凝土压顶时算至压顶上表面",false,{"key":16,"text":17,"correct":14},"B","砖基础的垫层通常包括在基础工程量中不另行计算",{"key":19,"text":20,"correct":21},"C","砖墙外凸出墙面的砖垛应按体积并入墙体内计算",true,{"key":23,"text":24,"correct":21},"D","砖地坪通常按设计图示尺寸以面积计算",{"key":26,"text":27,"correct":14},"E","通风管、垃圾道通常按图示尺寸以长度计算","CD","本题考查的是。选项A错误，围墙的高度算至压顶上表面（如有混凝土压顶时算至压顶下表面），围墙柱并入围墙体积内计算；选项B错误，垫层主要指除混凝土垫层外的其他材质的垫层，没有包括垫层要求的清单项目应按该垫层项目编码列项，例如：砖砌垫层、砂垫层、灰土垫层、楼地面等（非混凝土）垫层等。其工程量按设计图示尺寸以立方米计算；选项E错误，附墙烟囱、通风道、垃圾道应按设计图示尺寸以体积（扣除孔洞所占体积）计算并入所依附的墙体体积内。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]