[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894517":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894517,580,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》（GB 50854—2013），现浇混凝土构件工程量计算正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","构造柱按柱断面尺寸乘以全高以体积计算，嵌入墙体部分不计",false,{"key":16,"text":17,"correct":14},"B","框架柱工程量按柱基上表面至柱顶以高度计算",{"key":19,"text":20,"correct":21},"C","梁按设计图示尺寸以体积计算，主梁与次梁交接处按主梁体积计算",true,{"key":23,"text":24,"correct":14},"D","混凝土弧形墙按垂直投影面积乘以墙厚以体积计算",{"key":26,"text":27,"correct":21},"E","挑檐板按设计图示尺寸以体积计算","CE","构造柱按全高计算，嵌接墙体部分并入柱身体积，A错。框架柱工程量以体积来计量，B错。现浇混凝土梁按设计图示尺寸以体积计算。梁长的确定：梁与柱连接时，梁长算至柱侧面；主梁与次梁连接时，次梁长算至主梁侧面。挑檐板按设计图示尺寸以体积计算。现浇混凝土墙按设计图示尺寸以体积计算。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]