[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894515":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894515,580,2,"多选题","根据《房屋建筑与装饰工程工程量清单计算规范》（GB50854-2013）规定，关于现浇砼构件工程量计算正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","电缆沟、地沟按设计图示尺寸以面积计算",false,{"key":16,"text":17,"correct":18},"B","台阶按设计图示尺寸以水平投影面积或体积计算",true,{"key":20,"text":21,"correct":14},"C","压顶按设计图示尺寸以水平投影面积计算",{"key":23,"text":24,"correct":18},"D","扶手按设计图示尺寸以体积计算",{"key":26,"text":27,"correct":18},"E","检查井按设计图示尺寸以体积计算","BDE","电缆沟、地沟按设计图示以中心线长度计算。扶手、压顶工程量以米计量时，按设计图示的中心线延米计算;以立方米计量时，按设计图示尺寸以体积计算。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]