[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894485":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894485,580,2,"多选题","编排施工图纸应遵循的顺序是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","全局性图纸在前，局部详图在后",true,{"key":16,"text":17,"correct":14},"B","先施工的在前，后施工的在后",{"key":19,"text":20,"correct":14},"C","布置图在前，构件图在后",{"key":22,"text":23,"correct":14},"D","重要图纸在前，次要图纸在后",{"key":25,"text":26,"correct":27},"E","布置图在后，构件图在前",false,"ABCD","一般一套完整的施工图的排列顺序是图纸目录、施工总说明、建筑总平面图、建筑施工图、结构施工图、给水排水施工图、采暖通风施工图、电气施工图等。其中各专业图纸也应按照一定的顺序编排，其总的原则是：①全局性图纸在前，局部详图在后；②先施工的在前，后施工的在后；③布置图在前，构件图在后；④重要图纸在前，次要图纸在后。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]