[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894470":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894470,580,2,"多选题","下列有关施工组织设计的表述，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工平面图是施工方案及施工进度计划在空间上的全面安排",true,{"key":16,"text":17,"correct":18},"B","单位工程施工组织设计是指导分部分项工程施工的依据",false,{"key":20,"text":21,"correct":14},"C","只有在编制施工总进度计划后才可编制资源需求量计划",{"key":23,"text":24,"correct":14},"D","对于简单工程，可以只编制施工方案及施工进度计划和施工平面图",{"key":26,"text":27,"correct":18},"E","只有在编制施工总进度计划后才可制订施工方案","ACD","A项，施工平面图是施工方案及施工进度计划在空间上的全面安排。B项，单位工程施工组织设计是以单位工程为对象编制的，在施工组织总设计的指导下，由直接组织施工的单位根据施工图设计进行编制，用以直接指导单位工程的施工活动，是施工单位编制分部（分项）工程施工组织设计和季、月、旬施工计划的依据。C项，只有在编制施工总进度计划后才可编制资源需求量计划。D项，对于简单的工程，一般只编制施工方案，并附以施工进度计划和施工平面图。E项，拟订施工方案后才可编制施工总进度计划。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]