[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894469":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894469,580,2,"多选题","下列施工组织设计的内容中，属于施工部署与施工方案内容的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","安排施工顺序",true,{"key":16,"text":17,"correct":14},"B","比选施工方案",{"key":19,"text":20,"correct":21},"C","计算主要技术经济指标",false,{"key":23,"text":24,"correct":21},"D","编制施工准备计划",{"key":26,"text":27,"correct":21},"E","编制资源需求计划","AB","施工部署及施工方案的内容包括：①根据工程情况，结合人力、材料、机械设备、资金、施工方法等条件，全面部署施工任务，合理安排施工顺序，确定主要工程的施工方案；②对拟建工程可能采用的几个施工方案进行定性、定量的分析，通过技术经济评价，选择最佳方案。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]