[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894468":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894468,580,2,"多选题","下列关于工程项目施工组织设计，正确的说法是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工组织设计是纯技术性文件",false,{"key":16,"text":17,"correct":14},"B","施工组织设计必须在投标前编制完成",{"key":19,"text":20,"correct":21},"C","施工组织设计可作为项目管理规划文件",true,{"key":23,"text":24,"correct":21},"D","施工组织设计可用做施工前的准备工作文件",{"key":26,"text":27,"correct":14},"E","施工组织总设计应由设计单位编制","CD","本题考查的是施工组织设计概述。选项A错误，施工组织设计是技术、管理、经济全局性文件；选项B错误，中标后以施工合同和中标施工组织设计为依据，为满足施工准备和施工需要编制的施工组织设计，即实施性施工组织设计；选项E错误，施工组织总设计，由施工单位编制。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]