[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894466":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894466,580,2,"多选题","编制施工组织总设计时，通常要对整个建设过程进行施工部署，其主要工作应包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","组织各种物资",false,{"key":16,"text":17,"correct":18},"B","确定工程开展程序",true,{"key":20,"text":21,"correct":18},"C","拟定总体施工方案",{"key":23,"text":24,"correct":18},"D","明确施工任务划分与组织安排",{"key":26,"text":27,"correct":18},"E","编制施工准备工作计划","BCDE","本题考查的是施工组织总设计。施工部署的内容和侧重点根据建设项目的性质、规模和客观条件不同而有所不同。一般应包括下列内容：对项目总体施工做出部署；明确施工任务划分及组织管理；编制施工准备工作计划；总体施工方案的拟定；确定工程开展程序。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]