[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894464":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894464,580,2,"多选题","单位工程施工组织设计中所涉及的技术组织措施应包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","降低成本措施",true,{"key":16,"text":17,"correct":18},"B","节约工期的措施",false,{"key":20,"text":21,"correct":14},"C","季节性施工措施",{"key":23,"text":24,"correct":14},"D","防止环境污染的措施",{"key":26,"text":27,"correct":18},"E","保证资源供应的措施","ACD","本题考查的是单位工程施工组织设计。技术组织措施的设计：①保证质量措施，保证“PDCA”循环（计划－执行－检查－处理）的正常运转；②安全施工措施，提出预防措施；③降低成本措施，应以施工预算为尺度，一定要正确处理降低成本、提高质量和缩短工期三者的关系；④季节性施工措施，冬期（保温、防冻）、雨期（防淋、潮、泡、淹）；⑤防止环境污染的措施，防废水、大气、固体、噪声等污染。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]