[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894461":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894461,580,2,"多选题","施工组织总设计、单位(单项)工程施工组织设计和分部(分项)工程施工组织设计的不同之处是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","目标",false,{"key":16,"text":17,"correct":14},"B","编制原则",{"key":19,"text":20,"correct":21},"C","编制的施工范围",true,{"key":23,"text":24,"correct":21},"D","依据的具体资料",{"key":26,"text":27,"correct":21},"E","要求的深度","CDE","施工组织总设计、单位(单项)工程施工组织设计和分部(分项)工程施工组织设计的目标是一致的，编制原则是一致的，主要内容是相通的。不同之处在于编制的施工范围不同、依据的具体资料不同、要求的深度不同、责任主体和所起的作用不同。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]