[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894431":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894431,580,2,"多选题","为了保证填土压实的效果，施工时应该采取的措施包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","由下至上分层铺填、分层压实",true,{"key":16,"text":17,"correct":14},"B","在填方时按设计要求预留沉降量",{"key":19,"text":20,"correct":14},"C","将透水性较大的土放在下层，透水性较小的土放在上层",{"key":22,"text":23,"correct":24},"D","将不同种类的填料混合拌匀后分层填筑",false,{"key":26,"text":27,"correct":14},"E","合理确定分层厚度及压实遍数","ABCE","本题考查的是土石方工程施工技术。填方宜采用同类土填筑，当采用不同透水性的土分层填筑时，下层宜填筑透水性较大、上层宜填筑透水性较小的填料。填方压实应由下至上分层铺填，分层压（夯）实。分层厚度及压（夯）实遍数，根据压（夯）实机械、密实度要求、填料种类及含水量确定。@##",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]