[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894429":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894429,580,2,"多选题","关于地下连续墙施工，说法正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","机械化程度高",true,{"key":16,"text":17,"correct":14},"B","既可挡土防水也可以作建筑的基础",{"key":19,"text":20,"correct":21},"C","必须放坡开挖，施工土方量大",false,{"key":23,"text":24,"correct":14},"D","相邻段接头部位容易出现质量问题",{"key":26,"text":27,"correct":14},"E","作业现场容易出现污染","ABDE","A选项正确，地下连续墙施工全盘机械化，速度快、精度高，并且振动小、噪声低。B选项正确，地下连续墙既可作为临时挡土、防水设施，也可以作为地面建筑的深基础，还可以作为地下建筑物的外墙使用。C选项错误，开挖基坑无需放坡，土方量小。D、E选项正确，每段连续墙之间的接头质量较难控制，往往容易形成结构的薄弱点，制浆及处理系统占地较大，管理不善易造成现场泥泞和污染。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]