[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894419":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894419,580,2,"多选题","下列关于屋面涂膜防水施工，表述错误的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","按先高后低原则进行",false,{"key":16,"text":17,"correct":14},"B","按涂料的品种分层逐遍涂布",{"key":19,"text":20,"correct":21},"C","屋面坡度小于15%的，胎体增强材料应平行于屋脊铺设",true,{"key":23,"text":24,"correct":21},"D","屋面坡度大于15%的，胎体增强材料可垂直于屋脊铺设",{"key":26,"text":27,"correct":14},"E","分隔缝处增设的胎体增强材料，宜空铺100mm的宽度","CD","本题考查的是建筑防水和保温工程施工技术。当需要铺设胎体增强材料时，屋面坡度小于15%的可平行屋脊铺设，屋面坡度大于15%的应垂直于屋脊铺设。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]