[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894305":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894305,580,1,"单选题","不属于招标控制价项目工程量计算依据的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","常规施工方案",false,{"key":16,"text":17,"correct":18},"B","施工方案",true,{"key":20,"text":21,"correct":14},"C","工程量计价规则",{"key":23,"text":24,"correct":14},"D","招标工程量清单","本题考查的是工程量计算的依据。（1）《计价规范》和《计量规范》；（2）本省建设行政主管部门颁发的有关计价规定：（3）建设工程设计文件及相关资料；（4）拟定的招标文件及招标工程量清单；（5）与建设工程有关的标准、规范、技术资料；（6）施工现场情况、工程特点及常规施工方案；（7）工程造价管理机构发布的市场信息价，没有市场信息价的参照市场价；（8）其他的相关资料。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]