[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894285":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894285,580,1,"单选题","正常的施工技术条件下，完成 单位合格产品所必需的人工消耗时间，称为（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工时间定额",true,{"key":16,"text":17,"correct":18},"B","人工产量定额",false,{"key":20,"text":21,"correct":18},"C","材料消耗定额",{"key":23,"text":24,"correct":18},"D","台班定额","时间定额是指在正常和合理使用机械的条件下，完成单位合格产品所必须的人工消耗时间。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]