[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894283":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},894283,580,1,"单选题","可以不采用工程量清单计价的项目的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","全部使用国有资金的投资项目",false,{"key":16,"text":17,"correct":14},"B","国有资金为主的投资项目",{"key":19,"text":20,"correct":14},"C","全部使用国家融资资金的项目",{"key":22,"text":23,"correct":24},"D","大型国企的自有资金投资的项目",true,"全部使用国有资金（含国家融资资金）投资或国有资金为主的项目必须采用工程量清单计价。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]