[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894280":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894280,580,1,"单选题","主要技术组织措施不包括（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","技术措施",false,{"key":16,"text":17,"correct":14},"B","质量保证措施",{"key":19,"text":20,"correct":21},"C","职业健康安全措施",true,{"key":23,"text":24,"correct":14},"D","进度控制措施","技术组织措施包括：技术措施、质量保证措施、安全施工保证措施、降低施工成本措施、进度控制措施、现场环境保护措施。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]