[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894256":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894256,580,1,"单选题","下列不属于混凝土预制桩沉桩工序的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","桩机安装",false,{"key":16,"text":17,"correct":18},"B","配制泥浆",true,{"key":20,"text":21,"correct":14},"C","送桩",{"key":23,"text":24,"correct":14},"D","接桩","混凝土预制桩施工工艺为：施工准备、桩机安装、桩位探测、桩机行走、桩起吊、定位、安或拆桩帽、桩尖、打或压桩体、接桩、送桩、接下一根、基槽基坑开挖完成后的凿或截桩头。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]