[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894242,580,1,"单选题","采用不镑钢水落管排水时，执行镀锌钢管项目，材料按实际换算，人工乘以系数（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.6",false,{"key":16,"text":17,"correct":14},"B","0.8",{"key":19,"text":20,"correct":21},"C","1.1",true,{"key":23,"text":24,"correct":14},"D","1.2","本题考查的是《2017届房屋建筑与装饰工程预算定额》基本内容。采用不镑钢水落管排水时，执行镀锌钢管项目，材料按实际换算，人工乘以系数1.1。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]