[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894229":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894229,580,1,"单选题","满堂基础垫层底以下局部加深的槽坑，按槽坑相应规侧计算工程量，相应项目人工、机械乘以系数（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.25",true,{"key":16,"text":17,"correct":18},"B","0.90",false,{"key":20,"text":21,"correct":18},"C","1.43",{"key":23,"text":24,"correct":18},"D","1.15","本题考查的是《2017届房屋建筑与装饰工程预算定额》基本内容。满堂基础垫层底以下局部加深的槽坑，按槽坑相应规侧计算工程量，相应项目人工、机械乘以系数1.25。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]