[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894218":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894218,580,1,"单选题","招标人自行供应材料的，总承包服务费按招标人供应材料价值的（ ）计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1%",true,{"key":16,"text":17,"correct":18},"B","1.5%",false,{"key":20,"text":21,"correct":18},"C","3%",{"key":23,"text":24,"correct":18},"D","5%","本题考查的是工程费用定额。招标人自行供应材料的，总承包服务费按招标人供应材料价值的1%计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]