[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894217":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894217,580,1,"单选题","在工程施工中，由于不可抗力事件的发生，导致下列费用发生，需要由承包人承担的部分是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程所需清理、修复费用",false,{"key":16,"text":17,"correct":14},"B","应工程师要求留在施工场地的管理人员的费用",{"key":19,"text":20,"correct":21},"C","承包人施工人员的伤亡损失",true,{"key":23,"text":24,"correct":14},"D","在现场执行工作的发包方管理人员","本题考查的是工程价款结算和合同价款的调整。发生不可抗力后，承包人可以就不可抗力停工期间应监理人要求照管、清理、修复工程提出费用索赔，各自伤亡人员各自承担",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]