[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894212":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},894212,580,1,"单选题","编制招标控制价时，不可竞争的费用不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","安全文明施工费",false,{"key":16,"text":17,"correct":14},"B","规费",{"key":19,"text":20,"correct":14},"C","税金",{"key":22,"text":23,"correct":24},"D","夜间施工增加",true,"本题考查的是投标限价（最高投标报价）编制。不可竞争的费用按照国家有关规定计算，包括安全文明施工费、规费和税金。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]