[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894211":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894211,580,1,"单选题","措施项目组价的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","消耗量定额和价目表表现形式的组价",false,{"key":16,"text":17,"correct":18},"B","综合单价和费率形式的组价",true,{"key":20,"text":21,"correct":14},"C","消耗量定额和综合单价形式的组价",{"key":23,"text":24,"correct":14},"D","综合单价和价目表表现形式的组价","本题考查的是投标限价（最高投标报价）编制。措施项目应按招标文件中提供的措施项目清单确定，措施项目分为以“量”计算和以“项”计算两种。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]