[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894210,580,1,"单选题","编制招标控制价时，下列关于综合单价的确定方法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量清单综合单价=∑定额项目合价\u002F工程量清单项目工程量，不考虑未计价材料费用",true,{"key":16,"text":17,"correct":18},"B","工程设备、材料价格的市场风险，考虑一定率值的风险费用，纳入到综合单价中",false,{"key":20,"text":21,"correct":18},"C","税金、规费等法律、法规、规章和政策变化风险和人工单价等风险费用，不应纳入综合单价",{"key":23,"text":24,"correct":18},"D","综合单价中应包括暂估价中的材料和工程设备暂估单价","本题考查的是投标限价（最高投标报价）编制。选项A错误，工程量清单综合单价＝[∑定额项目合价＋未计价材料]\u002F工程量清单项目工程量。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]